In August and September 2019, JSC Belaruskali will carry out repair works on the winding engine of the fourth shaft and process sections on its Production Unit 3. This will result in the reduced production of pink product.

At the same time, the producer plans sequential turnarounds of two technological lines on Production Unit 4, which will lead to a decrease in the output of white product.

In September, a major turnaround is planned on Production Unit 3, in October – on Production Unit 4. In late October or early November, a major turnaround will be carried out on Production Unit 2. Specific dates and period of turnarounds will be determined in each case based on the required amount of work.